Tasting Room Construction Project

This page will have periodic updates for the ongoing Tasting Room construction project

May 15 Tasting Room update and more!

Quick update because it’s late …

Siding is now finished on front (west) and south side, and moving along on back/east side. If weather doesn’t ‘interrupt’, siding could finish this week.
All the interior window trim is installed, and much of the door trim.
All but 3 of the interior doors are installed, and the rest should be done this week.
New roof on whole building scheduled to be installed Tuesday 5/21.
Electricians return next Wednesday 5/23 to finish all their work … finish installing rest of lights (mostly outside, after siding done, but also in ceiling in covered portion of deck).
Concrete pad poured under deck – to facilitate bring pallets of wine into basement.

And on the wine side .. the ‘interim tasting room’ in the vineyard barn is open 11-6 Thurs/Fri/Saturday.

And in the next week or two we’ll be bottling 10 different wines from the 2023 harvest … whites and rose .. including two ‘bubblies’ … and our first issue of Rkatsiteli.
And the much waited for ‘Betty’s Blend White’ named after my mom, with her picture on the front label! Blend of Chardonnay, Riesling, Gewurztraminer and Rkatsiteli!

May 5 Tasting Room update

I’ve been so busy I’ve been negligent posting updates.

If you’re a Facebook user, Noah regularly puts updates there – https://www.facebook.com/airyacresvines

April and last week saw huge progress.

The exterior doors arrived and were installed.

The deck and roof over south half of deck, and the handicap ramp were finished

All but 4 of the interior lights were installed (I ordered 4 too few; still can’t count well :))

Porcelain tile finished (south side first floor plus inside front door/bottom of stairs), and grout should go in this week.

Vinyl flooring finished on south side upstairs and about 75% of north side.

The rest of the windows were installed, and the exterior trim done on all the window.

The siding will start going up this week … today!

And a bee hive was ‘planted’ on the farm about a week ago!

And here’s a walk thru taken a week or so ago – before some of this work was completed – https://youtu.be/iIbGRCb0e5Q
The submittal to Seneca County for the well water treatment (as a tasting room it become a ‘public’ water system) was handed in last Thursday. Hopefully it gets approved quickly so installation can occur..
And the post and cables for the deck railing were ordered last week.
Those could well be the last two ‘hurdles’ for getting the official green light from the county to open to the public.

April 15 Tasting Room Project Update

Work on the Tasting Room has really accelerated in the last 2 weeks.

The deck framing is complete. The siding arrives Tuesday or Wednesday, and should start being installed quickly.
The porcelain tiles are about 75% installed, and the vinyl tiles for the rest of the building arrived today.
The handicap ramp was framed last Friday.
The electricians come Tuesday to install light fixtures, switches and outlets.

April 10 Tasting Room Project Update

Making much progress now.

Back deck construction started Tuesday, and much progress made in 2 days. Decking scheduled to arrive next Tuesday. After decking installed the east windows (view over vineyard) will be installed.

Porcelain tile installation also started Tuesday. Should finish in 4-5 days.

Here’s link to some pictures, including the view from the deck.

https://link.shutterfly.com/zkcC7pXbHIb

(use the ‘slide show’ icon for easy viewing – )

Some of the fire/alarm wiring device installation done.

Rest of floor tiles scheduled to arrive by end of this week.

Parking lot work scheduled to start next Tuesday (bulldozer dropped off this Tuesday)

All lighting ordered, and expected to arrive by next Tuesday.

All siding ordered and installation should start in next week or two.

All doors on order, arriving different dates between mid-late April.

A lot of new work should be done in next few weeks!

April 1 Tasting Room Renovations Update

It’s been too long since giving a tasting room renovation update.
The drywall work took much longer than scheduled for a variety of reasons.
But it’s done now, and the painting was completed last week.
Here are some pictures of the windows installation that started today, April 1. I’ll post some more when they’re all done.

https://link.shutterfly.com/o4lQOvVesIb

And here’s a ‘walking tour’ of the inside, starting on the 2nd floor in the south side office/storage room.

https://youtu.be/bXraGnnGjXE

Much will be happening in the next few weeks!
Unless delayed by rain, all the windows should be in this week (except maybe the ones high up on 2nd floor east side).
New deck construction starts next Tuesday.
I’m ordering flooring material, deck material, most doors and all the lights this week.
There’s a lot left to do aiming for an opening by end of May … and absolutely ready for Noah and Katie’s wedding reception on June 18!

Tasting Room Renovations Update February 24, 2024

I realized recently it’s been over a month since I posted an update.

The focus since then has been ALL the drywall work. Like 9,000 square feet of drywall between all the walls and ceilings. So here’s a link to some recent progress pictures, and a video.

Drywall ‘mudding’ should finish in a few days, and then everything gets painted. After that windows will go in, and much more.

Meanwhile, life in the vineyard continues. Pruning is the big focus now. Son-in-law Nate is now the full time Vineyard Manager. With the help of his four legged ‘sidekick’ Annie.

And the ‘interim tasting room’ is open Saturday’s from 11-6.

 

January 15 Tasting Room Project Update

Last update was on Dec. 31st.
Much progress since then, and since a couple friends have asked, here’s an update!

Short version: Well working w/water in the building! Drywall started, ~25% done. Rough plumbing done.

Nate and I worked on getting the new well connected into the basement of the tasting room. Few pictures taken. As I believe I mentioned previously, the new well is across the road from the tasting room building. So a contractor used a horizontal drilling machine to pull two 1″ polypropylene pipes under the road. So we needed to dig a 4′ deep trench (protect water line from freezing) from where the pipe came out of the ground (and back far enough to where it was 4′ down) at both ends … one end to get a trench to edge of basement, and at other end to get trench to well. Then place the pipe into the trench, connect it to the well (4′ down) at well and house. There were 2 pipes, one for water and one for electric to run the pump. We got the wire thru it’s pipe from the well and into the basement, and the water pipe connected to the pitless adaptor at the well, and run into the house thru the basement wall (a sleeve put there when the basement wall was poured back in August).  And finally last weekend I got the piping and pressure tank and electric connected in the basement and voila we have water in the building! In a week or so the well driller will come and do a 6 hour flow test on the well as required by the country. After that, with the water hopefully cleared up from the well drilling debris, I’ll take samples to be tested for a variety of possible contaminants, as again required by the county. Based on the test results, a water treatment system will be designed. If nothing unusual is found, it will most likely mean standard particulate filters followed by a water softener and a UV lamp (sterilization).

The drywall work started around January 8, and as of today (Jan. 15) they’re about 1/4 done … with the 1st floor tasting room nearly complete. Pictures here.

And if someone wants to take the time, here are 48 pictures taken of all the walls before drywalling started .. to document where all the electric and fire alarm boxes are in the walls.

Although I don’t have any pictures, the rough plumbing work (drains, hot and cold water) finished up last Friday. This also needed to be done before the drywall was installed.

The drywall is planned to be done by end of next week, end of month at the latest. After that will be painting the drywall, the electricians come back to put the outlets and switches in the electric boxes, and the lights in ceiling and walls.  Also about them the new subflooring will be installed throughout the building, probably in early February. By then the windows hopefully will be here, and they’ll get installed in February sometime. After that would be new flooring and trim/molding around windows and the walls at floor.

Dec. 31 Tasting Room Project Update

2023 is drawing to a close, but Airy Acres Tasting Room construction continues, aiming for May opening!

Here’s a series of pictures of the 2023 journey for the house. – https://link.shutterfly.com/1KQdZcJBXFb

And here’s a list of the major work done:

  • In January, starting with a ~3500 sq. ft. house full 3 or 4 generations of family ‘stuff’, completely emptied so all the lath & plaster (and 2 chimneys) and some walls could be removed
  • In February, with the house empty, the contractor removed all the lath and plaster on the walls, and most of the electric and plumbing in the walls
  • Then 3 smaller additions (done sometime after main house built) were torn off – single story kitchen area, an enclosed porch and a screened in porch
  • Here’s a video tour in July, after most of the demolition work done.
  • After a few months finding the right contractors, the south half of the house, which had only a very shallow dirt crawl space, was set on I-beams so the dirt could be dug out and a new foundation wall built under that part of the house to create more basement space, mainly for storing cased wine
  • After necessary supports installed, the old field stone foundation wall separating the old and new basements was removed
  • A new concrete floor was poured in whole basement – the combined existing basement space and the new space. Here’s a video of it.
  • In October new electric power lines were run underground from the main feed at the vineyard barn
  • Then in November our main contractor returned, and finished removing all the old siding and installed new exterior sheathing (with 1″ insulation) over the entire structure – getting the building ‘weather tight’ for the winter
  • Then the interior wall renovations began – removing existing walls and adding new ones to create the new floor/room layout. Here’s a video tour, and another video tour.
  • About that time a new well was drilled to supply water for the tasting room building (across the road, so horizontal driller hired to install two 1″ polypro lines under Footes Corners Road – one for water from well to house, and one for the power line from house to the pump)
  • After that, in early December, the new rough electric was installed throughout the building, and the new fire alarm wiring
  • Also in early December a mini-split was installed in the basement to keep it warm enough to store cased wine
  • In mid-December, 3″ of spray foam installed on all the walls and roof
  • And just this week (Dec. 28) rough plumbing started, Thursday. Most of the drainage mains are done. Next week finish that up and also the hot/cold water lines

Coming next will be:

  • Plumbing rough-in that started this week will get done.
  • Drywall installation will start the week of Jan. 8, maybe sooner.
  • The new windows are on order, should arrive late January, and installed soon after.
  • New floors in Feb. or March.
  • Come April new siding and deck on the back.