I’ve been so busy I’ve been negligent posting updates.
If you’re a Facebook user, Noah regularly puts updates there – https://www.facebook.com/airyacresvines
April and last week saw huge progress.
The exterior doors arrived and were installed.
The deck and roof over south half of deck, and the handicap ramp were finished
All but 4 of the interior lights were installed (I ordered 4 too few; still can’t count well :))
Porcelain tile finished (south side first floor plus inside front door/bottom of stairs), and grout should go in this week.
Vinyl flooring finished on south side upstairs and about 75% of north side.
The rest of the windows were installed, and the exterior trim done on all the window.
The siding will start going up this week … today!
And a bee hive was ‘planted’ on the farm about a week ago!