April 15 Tasting Room Project Update

Work on the Tasting Room has really accelerated in the last 2 weeks.

The deck framing is complete. The siding arrives Tuesday or Wednesday, and should start being installed quickly.
The porcelain tiles are about 75% installed, and the vinyl tiles for the rest of the building arrived today.
The handicap ramp was framed last Friday.
The electricians come Tuesday to install light fixtures, switches and outlets.