Making much progress now.
Back deck construction started Tuesday, and much progress made in 2 days. Decking scheduled to arrive next Tuesday. After decking installed the east windows (view over vineyard) will be installed.
Porcelain tile installation also started Tuesday. Should finish in 4-5 days.
Here’s link to some pictures, including the view from the deck.
https://link.shutterfly.com/zkcC7pXbHIb
(use the ‘slide show’ icon for easy viewing – )
Some of the fire/alarm wiring device installation done.
Rest of floor tiles scheduled to arrive by end of this week.
Parking lot work scheduled to start next Tuesday (bulldozer dropped off this Tuesday)
All lighting ordered, and expected to arrive by next Tuesday.
All siding ordered and installation should start in next week or two.
All doors on order, arriving different dates between mid-late April.
A lot of new work should be done in next few weeks!