It’s been too long since giving a tasting room renovation update.
The drywall work took much longer than scheduled for a variety of reasons.
But it’s done now, and the painting was completed last week.
Here are some pictures of the windows installation that started today, April 1. I’ll post some more when they’re all done.
https://link.shutterfly.com/o4lQOvVesIb
And here’s a ‘walking tour’ of the inside, starting on the 2nd floor in the south side office/storage room.
Much will be happening in the next few weeks!
Unless delayed by rain, all the windows should be in this week (except maybe the ones high up on 2nd floor east side).
New deck construction starts next Tuesday.
I’m ordering flooring material, deck material, most doors and all the lights this week.
There’s a lot left to do aiming for an opening by end of May … and absolutely ready for Noah and Katie’s wedding reception on June 18!